Home Pit Dewatering

    Pit Dewatering

    Pit Dewatering

    Location/Site Client Date Duration
    Bowen Basin {tag_client} 2011 8 Weeks

    Bowen Basin, Queensland

    Project/Overview
    To design, manufacture and commission 2 x high pressure pumps to dewater the major operating pits of the mine-site.

    Our Involvement
    • Design - The skid mounted pump and pipework
    • Manufacture - Within 8 weeks
    • Commission - On-site for 5 days, providing training, setup and start-up commissioning

    Outcomes/Benefits
    • High performance pump dewatered pit so that mining operations could continue
    • Fuel efficient at optimum performance
    • Reliable product, fully supported in the field